Commissioning and application software development
SYSTEM OF MAIN GAS PIPELINES OF UKHTA-TORZHOK. II LINE (YAMAL)
A set of commissioning works was carried out “idly” and “under load” at the facility “Dispatch Control System (DCS) of Gazprom Transgaz Ukhta” LLC as part of the construction of “Ukhta-Torzhok Gas Pipeline System. II line (Yamal)” in terms of the application software.
As part of this project, a set of works was carried out to create the Operational Dispatching Management System for the Central Control Point of the Production and Dispatch Service of Gazprom Transgaz Ukhta LLC in the new administrative building of Gazprom Transgaz Ukhta LLC.
Scope of work:
- application software was developed and configured based on SCADA PSI;
- commissioning was carried out;
- operational documentation was developed
Gazprom Avtomatizatsiya PJSC
Gazprom Avtomatizatsiya PJSC is a company that has been successfully operating for 58 years in the fuel and energy industry. Having started its operations in 1960 as a special design bureau for instrumentation, automation and telemetry of gas pipelines, today Gazprom Avtomatizatsiya is one of the key companies in the gas industry.
Today, having concluded an agreement with Gazprom Avtomatizatsiya PJSC, the customer receives a full range of work: from an investment plan to implementation and subsequent after-sales service.
The geographical distribution of specialized subsidiaries allows Gazprom Avtomatizatsiya PJSC to service the process facilities in almost all regions of Russia.
WE WORKED FOR
Komi Republic, Ukhta, Gazprom Avtomatizatsiya PJSC