PROJECTS

Construction and installation work
TECHNICAL RE-EQUIPMENT OF A CONVERTIBLE GAS COOLING UNIT OF A HYDROGEN PRODUCTION PLANT, WORKSHOP №03 OF THE REFINERY OF TAIF-NK PJSC
As part of this project, the following works were performed:
- installation of reinforced concrete structures;
- installation of metal structures;
- installation of air cooling devices (process design, TM);
- Installation of an air cooler unit automation system.
The implementation of this project made it possible to achieve the required cooling parameters of the process medium using a rather compact air cooler unit. This was achieved by the use of advanced technologies implemented during the construction of the facility
TAIF-NK OJSC
TAIF-NK OJSC produces motor fuels (gasoline, diesel fuel) fully corresponding to EURO-5 environmental standard
WE WORKED FOR
Nizhnekamsk, TAIF-NK JSC